The water systems New York's own documents tie to PFAS funding: what each project is, the amount the state printed, how far it has got, and the document that says so. Latest record Oct 22, 2026; page updated Nov 2, 2026.
Sources: EFC Board of Directors Oct. 22, 2026 Resolutions 3143-3145 (2026-10-22); EFC: Water Infrastructure Improvement & Intermunicipal Grant Awards 2024 (2024-11-01); EFC: Water Infrastructure Improvement & Intermunicipal Grant Awards 2025 (2025-12-19); FFY 2024 IUP ; FFY 2025 IUP ; Final Intended Use Plan, Drinking Water State Revolving Fund, Federal Fiscal Year 2025 (2024-10); Final Intended Use Plan, Drinking Water State Revolving Fund, Federal Fiscal Year 2026 (2025-10); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3040-3050), meeting of 20 (2024-08-22); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3051-3056), meeting of 20 (2024-10-10); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3063-3065), meeting of 20 (2025-01-23); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3071-3072), meeting of 20 (2025-04-17); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3073-3078), meeting of 20 (2025-05-22); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3079-3084), meeting of 20 (2025-06-26); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3085-3088), meeting of 20 (2025-08-14); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3092-3099), meeting of 20 (2025-10-30); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3100-3106), meeting of 20 (2025-12-11); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3111-3115), meeting of 20 (2026-03-12); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3116-3120), meeting of 20 (2026-04-16); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3121-3123), meeting of 20 (2026-05-21); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3131-3140-3142), meeting (2026-09-10); NYS Environmental Facilities Corporation Board Resolutions (Nos. 3132-3139), meeting of 20 (2026-08-06). Open funding rounds and rules for New York →
| Oct 22, 2026 | This project consists of the construction of a new Granular Activated Carbon (GAC) treatment system at the Hampton Bays Water District’s Plant No. 3. The GAC system will consist of four 12-foot diameter, 40,000-lb adsorption vessels as well as associated process piping, valves, and appurtenances to allow the vessels to be operated either in parallel or in series. The project also includes construction of an approximately 3,400 square foot treatment building to house the GAC system; an approximately 7,000 cubic foot leaching galley structure to contain process backwash from the GAC system; and upgrades to Well Nos. 3-1, 3-2, and 3-3. The project scope is further defined by the engineering report entitled, ″Engineering Report: Wellhead Treatment for the Removal of PFAS at Plant No. 3″, dated May 2026, by H2M architects + engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3144, 2026-10-22) | $4.71M | Source, p. 94 → |
| Nov 1, 2024 | Wellhead Treatment for the Removal of PFAS at Plant No. 3 2024 WIIA grant awarded (Governor's announcement) | $4.71M | Source → |
| Oct 22, 2026 | This project includes the construction of a new Advanced Oxidation Process (AOP) treatment system to remove 1,4-dioxane from Well No. 2A at the Oxhead Road Well Field. A granular activated carbon (GAC) adsorption system, consisting of two twelve-foot diameter pressure vessels, will also be installed to remove per- and polyfluoroalkyl substances in the raw water, to quench residual hydrogen peroxide, and to remove potential AOP byproducts. The project scope is further defined by the engineering report entitled, ″Construction of a Granular Activated Carbon Adsorption System to Remove Per - and Polyfluoroalkyl Substances and Construction of an Advanced Oxidation Process System to Treat 1,4-Dioxane at the Suffolk County Water Authority’s Oxhead Road Well Field Well No. 2A″, dated 2024 (Revised 2026), by the Suffolk County Water Authority, as may be updated, amended, supplemented, and approved by the New York State Department of Health Approved by EFC Board of Directors (Resolution 3144, 2026-10-22) | $1.8M | Source, p. 96 → |
| Oct 22, 2026 | This project consists of the installation of 9,000 linear feet (LF) of watermain and an additional 81 service connections. The project scope is further defined by the engineering report entitled, ″Proposal to Extend 9,000 Linear Feet of Water Main to the Suffolk County Department of Health Services Private Well Survey South River Road Expansion Area in Calverton, Town of Brookhaven″, dated 2023, by the Suffolk County Water Authority, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3144, 2026-10-22) | $772k | Source, p. 96 → |
| Aug 6, 2026 | This project includes the construction of two new 20,000 pound Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from Well No. 3 at the Hawkins Road Well Field & Pump Station. The vessels, along with all associated appurtenances, will be installed at the existing Hawkins Road pump station. The project is defined by the engineering report entitled ″Engineering Report – Granular Activated Carbon Adsorption System – Hawkins Road Well Field Well No. 3″ dated June 2024 (Revised April 2026) by the Suffolk County Water Authority, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3133, 2026-08-06) | $1.05M | Source, p. 12 → |
| Aug 6, 2026 | This project includes the construction of two new 20,000 pound Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from Well Nos. 2A & 3A at the Station Road Well Field. The vessels, along with all associated appurtenances, will be installed at the existing Station Road pump station. The project is defined by the engineering reports entitled ″Engineering Report – Construction of a Granular Activated Carbon Adsorption System to Remove Per- and Polyfluoroalkyl Substances at the Suffolk County Water Authority’s Station Road Well Field Well No. 2A″ and ″Engineering Report – Construction of a Granular Activated Carbon Adsorption System to Remove Per- and Polyfluoroalkyl Substances at the Suffolk County Water Authority’s Station Road Well Field Well No. 3A″ dated August 2023 (Revised April 2026) by the Suffolk County Water Authority, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3133, 2026-08-06) | $1.8M | Source, p. 12 → |
| Dec 11, 2025 | This project includes the construction of two new Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from Well No. 4A at the Blue Point Road Well Field. The vessels, along with all associated appurtenances, will be installed at the existing Blue Point Road pump station. The project is defined by the engineering report entitled ″Engineering Report – Granular Activated Carbon Adsorption Systems″ dated 2023 by the Suffolk County Water Authority (SCWA), as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | $900k | Source, p. 36 → |
| Dec 11, 2025 | This project includes the construction of two new Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from Well No. 2 at the Boyle Road Well Field. The vessels, along with all associated appurtenances, will be installed at the existing Boyle Road pump station. The project is defined by the engineering report entitled ″Engineering Report – Granular Activated Carbon Adsorption Systems″ dated 2023 by the Suffolk County Water Authority (SCWA), as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | $900k | Source, p. 36 → |
| Dec 11, 2025 | This project includes the construction of two new Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from Well No. 2 at the Foxcroft Lane Well Field. The vessels, along with all associated appurtenances, will be installed at the existing Foxcroft Lane pump station. The project is defined by the engineering report entitled ″Engineering Report – Granular Activated Carbon Adsorption Systems″ dated 2023 by the Suffolk County Water Authority (SCWA), as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | $900k | Source, p. 37 → |
| Oct 2025 | Connection of public water to residences in Calverton, Town of Brookhaven along South River road due to PFAS detection in private wells, Upgrade Distribution System Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 63 → |
| Oct 2025 | Connection of public water to residences in Calverton, Town of Brookhaven along South River road due to PFAS detection in private wells, Upgrade Distribution System On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 170 → |
| Oct 10, 2024 | This project consists of installing 21,000 linear feet of water main in the Hamlet of Calverton. This extension will connect 98 homes to public water that currently obtain water from PFAS-impacted private wells. 12-inch ductile iron piping will be installed as part of this project to convey water, and the residences will be served by 1-, 1.5-, and 2-inch copper and high-density polyethylene (HOPE) water service lines from the new water main to the residences. Water meters will be installed on the new connections as part of this project. The project scope is further defined by the report entitled "Engineering Report - Distribution System Improvement Extension of Water Service" dated August 2022, by the Suffolk County Water Authority as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3053, 2024-10-10) | $1.85M | Source, p. 99 → |
| Oct 2024 | Connection of public water to residences in Calverton, Town of Brookhaven along South River road due to PFAS detection in private wells, Upgrade Distribution System Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $6.85M | Source, p. 60 → |
| Oct 2024 | Water main extension to 64 homes with PFAS contaminated private wells along Old Country Road Area, Extend Distribution System On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $2.48M | Source, p. 161 → |
| Oct 2024 | Connection of public water to residences in Calverton, Town of Brookhaven along South River road due to PFAS detection in private wells, Upgrade Distribution System On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $6.85M | Source, p. 162 → |
| Sep 10, 2026 | This project consists of an interconnection between the Dutchess County Water and Wastewater Authority (DCWWA) Hyde Park Regional Water System (Hyde Park) and the Quaker Hill Water System (Quaker Hill), including installation of approximately 29,500 feet of 8-inch water main, hydrants, valves and appurtenances; construction of a prefabricated booster pump station and a new electrical service at the proposed North Park parcel; and replacement of approximately 500 feet of 8-inch water main in the Quaker Hill distribution system. The project scope is further defined by the engineering report entitled, ″Quaker Hill PFAS Violation Remedy″, dated April 2026, by T&B Engineering and Landscape Architecture, P.C., as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3140, 2026-09-10) | $15.7M | Source, p. 11 → |
| Sep 10, 2026 | This project consists of an interconnection between the Dutchess County Water and Wastewater Authority (DCWWA) Hyde Park Regional Water System (Hyde Park) and the Quaker Hill Water System (Quaker Hill), including installation of approximately 29,500 feet of 8-inch water main, hydrants, valves and appurtenances; construction of a prefabricated booster pump station and a new electrical service at the proposed North Park parcel; and replacement of approximately 500 feet of 8-inch water main in the Quaker Hill distribution system. The project scope is further defined by the engineering report entitled, ″Quaker Hill PFAS Violation Remedy″, dated April 2026, by T&B Engineering and Landscape Architecture, P.C., as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3140, 2026-09-10) | $15.3M | Source, p. 16 → |
| Dec 19, 2025 | Rothkranz Street Water Main Extension For PFAS Mitigation and Regional Water Supply Expansion 2025 WIIA grant awarded (Governor's announcement) | $1.02M | Source → |
| Nov 1, 2024 | Quaker Hill Water System Interconnection to Hyde Park Regional Water System to Remedy PFAS-Contaminated Source Water 2024 WIIA grant awarded (Governor's announcement) | $15.3M | Source → |
| Sep 10, 2026 | This project consists of the installation of a granular activated carbon (GAC) treatment system to remove PFAS from Well No. 5-2A. The project scope is further defined by the engineering report entitled, ″Wellhead Treatment for the Removal of PFAS Compounds at Well No. 5-2A″, dated May 2025, by H2M architects + engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3140, 2026-09-10) | $2.33M | Source, p. 14 → |
| Oct 2025 | WD Extension - Forge Rd MHPs due to PFOA/PFOS and Mn contamination in private wells, Extend Distribution System, Extend Water District Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $1.19M | Source, p. 52 → |
| Oct 2025 | WD Extensions - Manorville (Ext #94) due to MTBE, PFOA, PFOS, and Fe/Mn contamination in private wells, Extend Distribution System, Extend Water District Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $12.9M | Source, p. 74 → |
| Oct 2025 | WD Extension Nos. 95 & 96 - Calverton. Extend Public Water to Address PFAS in Private Residential Wells., Extend Distribution System, Extend Water District Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $12.2M | Source, p. 74 → |
| Oct 2025 | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $2.33M | Source, p. 79 → |
| Oct 2025 | WD Extension - Forge Rd MHPs due to PFOA/PFOS and Mn contamination in private wells, Extend Distribution System, Extend Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $1.19M | Source, p. 169 → |
| Oct 2025 | WD Extension Nos. 95 & 96 - Calverton. Extend Public Water to Address PFAS in Private Residential Wells., Extend Distribution System, Extend Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $12.2M | Source, p. 170 → |
| Oct 2025 | WD Extensions - Manorville (Ext #94) due to MTBE, PFOA, PFOS, and Fe/Mn contamination in private wells, Extend Distribution System, Extend Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $12.9M | Source, p. 170 → |
| Oct 2025 | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $2.33M | Source, p. 172 → |
| Aug 14, 2025 | This project consists of the installation of Granular Activated Carbon (GAC) for the removal of PFAS at Plant No. 5. The project is defined by the engineering report entitled ″Installation of Wellhead Treatment for the Removal of Perfluorinated Compounds at Plant No. 5″ dated April 2021 by the engineering firm H2M architects + engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3087, 2025-08-14) | $1.32M | Source, p. 18 → |
| Oct 2024 | WD Extension - Forge Rd MHPs due to PFOA/PFOS and Mn contamination in private wells, Extend Distribution System, Extend Water District Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $1.19M | Source, p. 51 → |
| Oct 2024 | WD Extensions - Manorville (Ext #94) due to MTBE, PFOA, PFOS, and Fe/Mn contamination in private wells, Extend Distribution System, Extend Water District Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $12.9M | Source, p. 69 → |
| Oct 2024 | WD Extension Nos. 95 & 96 - Calverton. Extend Public Water to Address PFAS in Private Residential Wells., Extend Distribution System, Extend Water District Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $12.2M | Source, p. 70 → |
| Oct 2024 | Well No. 5-1 PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $2.2M | Source, p. 55 → |
| Oct 2024 | WD Extension Nos. 95 & 96 - Calverton. Extend Public Water to Address PFAS in Private Residential Wells., Extend Distribution System, Extend Water District On the FFY2025 BIL-GS Eligible Project List (amount is the project cost) | $12.2M | Source, p. 103 → |
| Oct 2024 | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant On the FFY2025 BIL-GS Eligible Project List (amount is the project cost) | $2.33M | Source, p. 104 → |
| Oct 2024 | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $2.33M | Source, p. 109 → |
| Oct 2024 | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $2.33M | Source, p. 74 → |
| Oct 2024 | WD Extension - Forge Rd MHPs due to PFOA/PFOS and Mn contamination in private wells, Extend Distribution System, Extend Water District On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $1.19M | Source, p. 160 → |
| Oct 2024 | Well No. 5-1 PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $2.2M | Source, p. 162 → |
| Oct 2024 | WD Extension Nos. 95 & 96 - Calverton. Extend Public Water to Address PFAS in Private Residential Wells., Extend Distribution System, Extend Water District On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $12.2M | Source, p. 162 → |
| Oct 2024 | WD Extensions - Manorville (Ext #94) due to MTBE, PFOA, PFOS, and Fe/Mn contamination in private wells, Extend Distribution System, Extend Water District On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $12.9M | Source, p. 162 → |
| Oct 2024 | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $2.33M | Source, p. 163 → |
| Undated | Well No. 5-2A PFAS removal, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $2.33M | Source, p. 2 → |
| Undated | WD Extension Nos. 95 & 96 - Calverton. Extend Public Water to Address PFAS in Private Residential Wells., Extend Distribution System, Extend Water District BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| May 21, 2026 | This project includes upgrading the existing water treatment facility to an ultrafiltration plant with granular activated carbon (GAC) contactors to ensure proper treatment of source water to address harmful algal blooms (HABs), PFOA/PFOS, and high turbidity. Additionally, the pump station and filter building will be upgraded as part of this project and the chlorine disinfection system will be converted from gas chlorine to liquid sodium hypochlorite. The project is defined by the engineering report entitled ″WTP Improvements″ dated September 2021 by the engineering firm MRB Group, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3122, 2026-05-21) | $11.8M | Source, p. 38 → |
| May 21, 2026 | This project includes upgrading the existing water treatment facility to an ultrafiltration plant with granular activated carbon (GAC) contactors to ensure proper treatment of source water to address harmful algal blooms (HABs), PFOA/PFOS, and high turbidity. Additionally, the pump station and filter building will be upgraded as part of this project and the chlorine disinfection system will be converted from gas chlorine to liquid sodium hypochlorite. The project is defined by the engineering report entitled ″WTP Improvements″ dated September 2021 by the engineering firm MRB Group, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3122, 2026-05-21) | $3M | Source, p. 40 → |
| May 21, 2026 | This project consists of the construction of two new Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from the Village of Valatie’s four developed groundwater supply wells. Additional work includes construction of a centralized treatment facility adjacent to the Village’s wastewater treatment plant to house the proposed GAC vessels and accommodate treatment currently required for the four wells. The project scope is further defined by the Basis of Design Report dated September 2025, by Weston & Sampson PE, LS, LA, Architects, PC as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3122, 2026-05-21) | — | Source, p. 39 → |
| May 21, 2026 | This project consists of the construction of two new Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from the Village of Valatie’s four developed groundwater supply wells. Additional work includes construction of a centralized treatment facility adjacent to the Village’s wastewater treatment plant to house the proposed GAC vessels and accommodate treatment currently required for the four wells. The project scope is further defined by the Basis of Design Report dated September 2025, by Weston & Sampson PE, LS, LA, Architects, PC as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3122, 2026-05-21) | $5.53M | Source, p. 41 → |
| Dec 19, 2025 | PFAS Treatment Facility 2025 WIIA grant awarded (Governor's announcement) | $5.53M | Source → |
| Oct 2025 | New filtration and PFAS treatment facility., New Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $3.94M | Source, p. 60 → |
| Oct 2025 | New filtration and PFAS treatment facility., New Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $3.94M | Source, p. 133 → |
| Oct 2024 | New filtration and PFAS treatment facility., New Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $3.94M | Source, p. 57 → |
| Oct 2024 | New filtration and PFAS treatment facility., New Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $3.94M | Source, p. 125 → |
| Undated | New filtration and PFAS treatment facility., New Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $2.76M | Source, p. 2 → |
| Apr 16, 2026 | This project consists of the installation of four (4) new granular activated carbon (GAC) pressure vessels each containing 40,000 pounds of F-300AR carbon media to remove perfluorooctanesulfonic acid (PFOS), perfluorooctanoic acid (PFOA) and other volatile organic compounds (VOCs) from the raw water of the District’s Wells 10 and 15. Additional work includes the construction/installation of a new treatment building, site piping, drainage modifications, instrumentation and controls integration, new pH adjustment treatment system, new 6,000 gallon underground sodium hydroxide storage tank, and a new post-treatment disinfection system. The project scope is further defined by the engineering report entitled, ″Wellhead Treatment for PFAS & VOCs at Well No. 10 & 15″, dated September 2023, revised August 2025, by H2M Architects + Engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3116, 2026-04-16) | $3.19M | Source, p. 7 → |
| Oct 2025 | Wellhead Treatment for PFAS & VOCs at Well Nos 10 & 15, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $4.56M | Source, p. 55 → |
| Oct 2025 | Wellhead Treatment for PFAS & VOCs at Well Nos 10 & 15, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $4.56M | Source, p. 169 → |
| Oct 2024 | Wellhead Treatment for PFAS & VOCs at Well Nos 10 & 15, Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $4.56M | Source, p. 54 → |
| Oct 2024 | Wellhead Treatment for PFAS & VOCs at Well Nos 10 & 15, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $4.56M | Source, p. 108 → |
| Oct 2024 | Wellhead Treatment for PFAS & VOCs at Well Nos 10 & 15, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $4.56M | Source, p. 161 → |
| Undated | Wellhead Treatment for PFAS & VOCs at Well Nos 10 & 15, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $3.19M | Source, p. 2 → |
| Mar 12, 2026 | This project is for creation of the Morrisonville 2 Water District within the Town of Schuyler Falls and the installation of approximately 9,350 linear feet of water main and associated fittings, valving, hydrants, and meters to provide public water to 43 properties and an existing mobile home park along Sand Road that current rely on private wells with perfluoroalkyl and polyfluoroalkyl substances (PFAS) contamination. The project scope is further defined by the engineering report entitled ″Water System Improvements to Address Emerging Contaminants″ dated August 2022, by Barton & Loguidice, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3112, 2026-03-12) | $5M | Source, p. 21 → |
| Mar 12, 2026 | This project consists of the construction of two new Granular Activated Carbon (GAC) adsorption vessels to remove Perfluoroalkyl Substances (PFAS) from Well Nos. 1A and 2 at the Village’s Syracuse Street facility. Additional work includes construction of a building to house the new GAC vessels, demolition of the DPW garage, construction of a new DPW garage, and miscellaneous upgrades to the existing treatment and electrical systems. The project scope is further defined by the Basis of Design Report dated January 2024, by D&B Engineers and Architects as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3112, 2026-03-12) | $5M | Source, p. 21 → |
| Oct 30, 2025 | This project consists of installation of a new Granular Activated Carbon (GAC) adsorption treatment system for the removal of PFOA and PFOS from the Village of Williston Park’s Well No. 4. The project includes the construction of a set of two 40,000 lb GAC vessels as well as a new masonry building at the Well No. 4 facility to house the GAC treatment system; updates to the facility piping, power supply, chlorine injection system, and motor control center to accommodate the GAC treatment system; and replacement of the facility’s Packed Tower Aeration System booster pump to accommodate pressure losses through the GAC treatment system. The project scope is further defined by the engineering report entitled, ″PFAS Treatment at Well 4 Basis of Design Report″, dated August 2024, by D&B Engineers and Architects as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3094, 2025-10-30) | $5M | Source, p. 97 → |
| Oct 2025 | Well No.4 GAC PFAS treatment, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $8.68M | Source, p. 55 → |
| Oct 2025 | Wells No. 1A and No. 2 GAC PFAS treatment, New Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $14.2M | Source, p. 78 → |
| Oct 2025 | Well No.4 GAC PFAS treatment, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $8.68M | Source, p. 148 → |
| Oct 2025 | Wells No. 1A and No. 2 GAC PFAS treatment, New Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $14.2M | Source, p. 149 → |
| Nov 1, 2024 | PFAS Treatment at Well 4 2024 WIIA grant awarded (Governor's announcement) | $5M | Source → |
| Oct 2024 | Wells No. 1A and No. 2 GAC PFAS treatment, New Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $14.2M | Source, p. 73 → |
| Oct 2024 | Well No.4 GAC PFAS treatment, Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $8.68M | Source, p. 54 → |
| Oct 2024 | Well No.4 GAC PFAS treatment, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $8.68M | Source, p. 108 → |
| Oct 2024 | Well No.4 GAC PFAS treatment, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $8.68M | Source, p. 139 → |
| Oct 2024 | Wells No. 1A and No. 2 GAC PFAS treatment, New Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $14.2M | Source, p. 141 → |
| Undated | Wells No. 1A and No. 2 GAC PFAS treatment, New Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Dec 19, 2025 | New Well Source Development to Address PFAS Contamination and Inadequate Source Capacity 2025 WIIA grant awarded (Governor's announcement) | $5.02M | Source → |
| Oct 2025 | New well field to mitigate PFAS contamination; replacement of transmission main., New Ground Water Source, Upgrade Transmission On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $8.42M | Source, p. 53 → |
| Oct 2025 | New well field to mitigate PFAS contamination; replacement of transmission main., New Ground Water Source, Upgrade Transmission On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $8.42M | Source, p. 118 → |
| Oct 2025 | New well field to mitigate PFAS contamination; replacement of transmission main., New Ground Water Source, Upgrade Transmission On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $8.42M | Source, p. 133 → |
| Dec 11, 2025 | This project consists of installation of two granular activated carbon (GAC) adsorption treatment systems and associated appurtenances at Well 9 to treat perfluorooctanoic acid (PFOA) contamination. This project also includes the installation of a permanent treatment building to house the GAC vessels. Other work includes upgrades to the Well 9 pump and motor, as well as miscellaneous equipment upgrades and site improvements. The project scope is further defined by the engineering report dated June 2024, by H2M Architects and Engineers as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | $4.9M | Source, p. 30 → |
| Oct 2025 | Plant No. 9 - New GAC treatment for PFAS removal, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $7M | Source, p. 78 → |
| Oct 2025 | Plant No. 9 - New GAC treatment for PFAS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $7M | Source, p. 149 → |
| Oct 2024 | Plant No. 9 - New GAC treatment for PFAS removal, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $7M | Source, p. 108 → |
| Oct 2024 | Plant No. 9 - New GAC treatment for PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $7M | Source, p. 73 → |
| Oct 2024 | Plant No. 9 - New GAC treatment for PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $7M | Source, p. 141 → |
| Undated | Plant No. 9 - New GAC treatment for PFAS removal, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $4.9M | Source, p. 2 → |
| Dec 11, 2025 | This project consists of the upgrade of a surface water treatment plant to install two sets of granular activated carbon (GAC) filter vessels. A new building containing the GAC filter vessels and a clearwell will be installed to integrate the treatment with the existing filter units and chemical treatment. New pumps will be installed to convey water through the plant, and improvements to the site drainage and discharge capabilities will be installed. The project scope is further defined by the engineering report entitled ″PFAS Treatment at The Nyack Water Treatment Plant″ dated February 2021, by H2M Architects and Engineers, as may be updated, amended, supplemented, and approved by the New York Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | — | Source, p. 28 → |
| Dec 11, 2025 | This project consists of the upgrade of a surface water treatment plant to install two sets of granular activated carbon (GAC) filter vessels. A new building containing the GAC filter vessels and a clearwell will be installed to integrate the treatment with the existing filter units and chemical treatment. New pumps will be installed to convey water through the plant, and improvements to the site drainage and discharge capabilities will be installed. The project scope is further defined by the engineering report entitled ″PFAS Treatment at The Nyack Water Treatment Plant″ dated February 2021, by H2M Architects and Engineers, as may be updated, amended, supplemented, and approved by the New York Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | $2.78M | Source, p. 35 → |
| Oct 2025 | PFAS Treatment at Nyack Water Plant., New Other Expenses, New Other (OT) Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $4.75M | Source, p. 60 → |
| Oct 2025 | PFAS Treatment at Nyack Water Plant., New Other Expenses, New Other (OT) On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $4.75M | Source, p. 164 → |
| Oct 2024 | PFAS Treatment at Nyack Water Plant., New Other Expenses, New Other (OT) Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $4.75M | Source, p. 57 → |
| Oct 2024 | PFAS Treatment at Nyack Water Plant., New Other Expenses, New Other (OT) On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $4.75M | Source, p. 156 → |
| Dec 11, 2025 | This project consists of extending the boundaries of the Smithtown Water District (SWD) service area to provide water to residences with private wells contaminated with perfluoroalkyl substances (PFAS). The project includes installation of approximately 3,330 linear feet of distribution main and appurtenances in two locations to service a total of 26 single-family dwellings. The project scope is further defined by the engineering report entitled, ″Map & Plan Report for District Boundary and Water Main Extension – Oakside Drive and Landing Avenue″, dated May 2025, by H2M architects + engineers as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3101, 2025-12-11) | $998k | Source, p. 30 → |
| Oct 2025 | Extension of water district to serve PFAS contaminated private wells (Oakside Drive and Landing Ave), Extend Distribution System Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $1.43M | Source, p. 74 → |
| Oct 2025 | Extension of water district to serve PFAS contaminated private wells (Oakside Drive and Landing Ave), Extend Distribution System On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $1.43M | Source, p. 170 → |
| Oct 2024 | Extension of water district to serve PFAS contaminated private wells (Oakside Drive and Landing Ave), Extend Distribution System On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $1.43M | Source, p. 108 → |
| Oct 2024 | Extension of water district to serve PFAS contaminated private wells (Oakside Drive and Landing Ave), Extend Distribution System On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $1.43M | Source, p. 70 → |
| Oct 2024 | Extension of water district to serve PFAS contaminated private wells (Oakside Drive and Landing Ave), Extend Distribution System On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $1.43M | Source, p. 162 → |
| Undated | Extension of water district to serve PFAS contaminated private wells (Oakside Drive and Landing Ave), Extend Distribution System IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $998k | Source, p. 2 → |
| Oct 30, 2025 | This project consists of installation of a new Granular Activated Carbon (GAC) adsorption treatment system for the removal of PFOA from Well No. 1 of the Manhasset-Lakeville Water District’s Campbell Station. The project includes the construction of a set of two 40,000 lb GAC vessels as well as a new masonry building to house the GAC treatment system; new site piping and drainage modifications to accommodate the GAC treatment system; new wiring for the GAC treatment building power and controls; and replacement of the well pump as needed upon evaluation. The project scope is further defined by the engineering report entitled ″Engineering Report – PFAS Treatment for Campbell Well No. 1″ dated August 2023, by H2M Architects + Engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3094, 2025-10-30) | $2.83M | Source, p. 96 → |
| Oct 2025 | Removal of PFAS contamination at Spruce Ponds Plant., Upgrade Water Treatment Plant On the FFY2026 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $3.6M | Source, p. 77 → |
| Oct 2025 | Installation of GAC Treatment for PFAS at Manhasset Lakeville WD Campbell Well No. 1, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $4.72M | Source, p. 148 → |
| Oct 2025 | Removal of PFAS contamination at Spruce Ponds Plant., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $3.6M | Source, p. 149 → |
| Nov 1, 2024 | PFAS Treatment for Campbell Well No. 1 2024 WIIA grant awarded (Governor's announcement) | $2.83M | Source → |
| Oct 2024 | Removal of PFAS contamination at Spruce Ponds Plant., Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $3.6M | Source, p. 72 → |
| Oct 2024 | Installation of GAC Treatment for PFAS at Manhasset Lakeville WD Campbell Well No. 1, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $4.72M | Source, p. 140 → |
| Oct 2024 | Removal of PFAS contamination at Spruce Ponds Plant., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $3.6M | Source, p. 142 → |
| Oct 30, 2025 | This project consists of the installation of a Granular Activated Carbon (GAC) treatment system and an ion exchange (IX) treatment system for the removal of PFAS from the existing Community Drive Facility Wells. The project is defined by the engineering report entitled ″Wellhead Treatment for Emerging Contaminants at Community Drive Facility″ dated November 2024 by the engineering firm H2M architects + engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3094, 2025-10-30) | $5M | Source, p. 97 → |
| Oct 2025 | Installation of GAC and Anion Exchange treatment systems to remove PFAS, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $13.7M | Source, p. 149 → |
| Oct 2024 | Installation of GAC and Anion Exchange treatment systems to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $13.7M | Source, p. 142 → |
| Oct 2025 | Well No. 5 - GAC treatment for PFAS removal; and Replace PTAS, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $18.5M | Source, p. 78 → |
| Oct 2025 | Installation of GAC to treat PFAS at Shepherd Lane Well 1, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $9.69M | Source, p. 78 → |
| Oct 2025 | Installation of GAC to treat PFAS at Shepherd Lane Well 1, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $9.69M | Source, p. 148 → |
| Oct 2025 | Well No. 5 - GAC treatment for PFAS removal; and Replace PTAS, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $18.5M | Source, p. 149 → |
| Oct 2024 | Installation of GAC to treat PFAS at Shepherd Lane Well 1, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $9.69M | Source, p. 73 → |
| Oct 2024 | Well No. 5 - GAC treatment for PFAS removal; and Replace PTAS, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $18.5M | Source, p. 108 → |
| Oct 2024 | Well No. 5 - GAC treatment for PFAS removal; and Replace PTAS, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $18.5M | Source, p. 73 → |
| Oct 2024 | Well No. 5 - GAC treatment for PFAS removal; and Replace PTAS, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $18.5M | Source, p. 140 → |
| Oct 2024 | Installation of GAC to treat PFAS at Shepherd Lane Well 1, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $9.69M | Source, p. 141 → |
| Undated | Well No. 5 - GAC treatment for PFAS removal; and Replace PTAS, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Undated | Installation of GAC to treat PFAS at Shepherd Lane Well 1, Upgrade Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Oct 2025 | Birch Hill Acres - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $3M | Source, p. 64 → |
| Oct 2025 | Birch Hill Acres - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $3M | Source, p. 163 → |
| Oct 2024 | Birch Hill Acres - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $3M | Source, p. 61 → |
| Oct 2024 | Birch Hill Acres - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $3M | Source, p. 155 → |
| Oct 2025 | Installation of Ionization Media filters, interconnections within the Town's existing water districts, and development of new GW Sources to address PFOA/PFAS contamination, Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Distribution On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $16.7M | Source, p. 57 → |
| Oct 2025 | Installation of Ionization Media filters, interconnections within the Town's existing water districts, and development of new GW Sources to address PFOA/PFAS contamination, Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $16.7M | Source, p. 135 → |
| Aug 14, 2025 | This project consists of the installation of an ion exchange (IX) treatment system at the Hopewell Hamlet Water District (WD) to remove PFAS; construction of a new well at the Beekman wellfield; and the installation of interconnections throughout the town to interconnect several water districts. The project is defined by the engineering report entitled ″Town of East Fishkill Water Supply Project″ dated August 2023 (Revised January 2025) by the Town of East Fishkill, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3087, 2025-08-14) | $5M | Source, p. 15 → |
| Oct 2024 | Installation of Ionization Media filters, interconnections within the Town's existing water districts, and development of new GW Sources to address PFOA/PFAS contamination, Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Distribution On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $16.7M | Source, p. 56 → |
| Oct 2024 | Installation of Ionization Media filters, interconnections within the Town's existing water districts, and development of new GW Sources to address PFOA/PFAS contamination, Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $16.7M | Source, p. 127 → |
| Oct 2025 | Plant No. 1 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 78 → |
| Oct 2025 | Plant No. 1 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 149 → |
| Oct 2024 | Plant No. 1 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List | $0 | Source, p. 73 → |
| Oct 2024 | Plant No. 1 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) | $0 | Source, p. 141 → |
| Undated | Plant No. 1 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $605k | Source, p. 2 → |
| Oct 2025 | Install GAC to remove PFAS at Nancy Court Well Station., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $10.9M | Source, p. 148 → |
| Nov 1, 2024 | PFAS Treatment at the Nancy Court Well Station 2024 WIIA grant awarded (Governor's announcement) | $5M | Source → |
| Oct 2024 | Install GAC to remove PFAS at Nancy Court Well Station., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $10.9M | Source, p. 140 → |
| Oct 2025 | Installation of GAC for PFAS removal., Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $8.8M | Source, p. 56 → |
| Oct 2025 | Installation of GAC for PFAS removal., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $8.8M | Source, p. 165 → |
| Oct 2024 | Installation of GAC for PFAS removal., Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $8.8M | Source, p. 55 → |
| Oct 2024 | Installation of GAC for PFAS removal., Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $8.8M | Source, p. 108 → |
| Oct 2024 | Installation of GAC for PFAS removal., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $8.8M | Source, p. 157 → |
| Undated | Installation of GAC for PFAS removal., Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Oct 2025 | Interconnection of Greenfields Water System to Hyde Park Regional Water System to address PFAS contamination, Upgrade Water Treatment Plant, New Pump Station, New Inter-Connection Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 49 → |
| Oct 2025 | Interconnection of Greenfields Water System to Hyde Park Regional Water System to address PFAS contamination, Upgrade Water Treatment Plant, New Pump Station, New Inter-Connection Short-term loan closed (per FFY2026 Final IUP Multiyear List note) | $0 | Source, p. 135 → |
| Oct 2024 | Interconnection of Greenfields Water System to Hyde Park Regional Water System to address PFAS contamination, Upgrade Water Treatment Plant, New Pump Station, New Inter-Connection Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List | $0 | Source, p. 49 → |
| Oct 2024 | Interconnection of Greenfields Water System to Hyde Park Regional Water System to address PFAS contamination, Upgrade Water Treatment Plant, New Pump Station, New Inter-Connection Short-term loan closed (per FFY2025 Final IUP Multiyear List note) | $0 | Source, p. 127 → |
| Oct 2025 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $53.3M | Source, p. 54 → |
| Oct 2025 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2026 IIJA-GS Eligible Project List (amount is the project cost) | $53.3M | Source, p. 109 → |
| Oct 2025 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $53.3M | Source, p. 147 → |
| Nov 1, 2024 | Village of Hempstead Water Treatment Improvements Project 2024 WIIA grant awarded (Governor's announcement) | $37.3M | Source → |
| Oct 2024 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $53.3M | Source, p. 53 → |
| Oct 2024 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2025 BIL-GS Eligible Project List (amount is the project cost) | $53.3M | Source, p. 99 → |
| Oct 2024 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $53.3M | Source, p. 108 → |
| Oct 2024 | 1,4-dioxane and PFAS removal at Clinton Street Plant , Upgrade Water Treatment Plant, Upgrade Storage On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $53.3M | Source, p. 139 → |
| Oct 2025 | Plant No. 6 - AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal., Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 72 → |
| Oct 2025 | Plant 5 AOP treatment of 1,4-dioxane, PFOA and PFOS., Upgrade Other Expenses, New Water Treatment Plant, Upgrade Other (OT) On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $9.42M | Source, p. 148 → |
| Oct 2025 | Plant No. 6 - AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 148 → |
| Oct 2024 | Plant No. 6 - AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal., Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List | $0 | Source, p. 68 → |
| Oct 2024 | Plant 5 AOP treatment of 1,4-dioxane, PFOA and PFOS., Upgrade Other Expenses, New Water Treatment Plant, Upgrade Other (OT) On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $9.42M | Source, p. 140 → |
| Oct 2024 | Plant No. 6 - AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) | $0 | Source, p. 140 → |
| Oct 2025 | Relocate existing GAC vessels to Well 29 and install new GAC Vessels at Wells 18 and 19 to address PFAS contamination, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $17.6M | Source, p. 77 → |
| Oct 2025 | Well 12 PFAS removal, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $8.62M | Source, p. 77 → |
| Oct 2025 | New Wellhead Treatment for PFAS Removal at Well 23, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $10.4M | Source, p. 77 → |
| Oct 2025 | Installation of GAC for PFAS removal at Wells 27 & 28, Upgrade Water Treatment Plant On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $17.8M | Source, p. 118 → |
| Oct 2025 | New AOP and GAC Treatment at Well 3 to remove 1,4-dioxane and PFOA., Upgrade Water Treatment Plant On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $19.3M | Source, p. 118 → |
| Oct 2025 | New AOP and GAC Treatment at Well 3 to remove 1,4-dioxane and PFOA., Upgrade Water Treatment Plant On the FFY2026 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $19.3M | Source, p. 77 → |
| Oct 2025 | Installation of GAC for PFAS removal at Wells 27 & 28, Upgrade Water Treatment Plant On the FFY2026 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $17.8M | Source, p. 85 → |
| Oct 2025 | Well 17 PFAS Removal., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $10.5M | Source, p. 148 → |
| Oct 2025 | Installation of GAC for PFAS removal at Wells 27 & 28, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $17.8M | Source, p. 149 → |
| Oct 2025 | Well 12 PFAS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $8.62M | Source, p. 149 → |
| Oct 2025 | Well 13 PFAS Removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $12.6M | Source, p. 149 → |
| Oct 2025 | New AOP and GAC Treatment at Well 3 to remove 1,4-dioxane and PFOA., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $19.3M | Source, p. 149 → |
| Oct 2025 | Relocate existing GAC vessels to Well 29 and install new GAC Vessels at Wells 18 and 19 to address PFAS contamination, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $17.6M | Source, p. 149 → |
| Oct 2025 | New Wellhead Treatment for PFAS Removal at Well 23, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $10.4M | Source, p. 150 → |
| Oct 2024 | Relocate existing GAC vessels to Well 29 and install new GAC Vessels at Wells 18 and 19 to address PFAS contamination, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $17.6M | Source, p. 72 → |
| Oct 2024 | Well 12 PFAS removal, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $8.62M | Source, p. 72 → |
| Oct 2024 | Well 23 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $10.4M | Source, p. 108 → |
| Oct 2024 | Well 28 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $6.68M | Source, p. 108 → |
| Oct 2024 | Well 23 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $10.4M | Source, p. 72 → |
| Oct 2024 | Well 28 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $6.68M | Source, p. 72 → |
| Oct 2024 | Well 12 PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $8.62M | Source, p. 141 → |
| Oct 2024 | Well 23 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $10.4M | Source, p. 141 → |
| Oct 2024 | Well 13 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $12.6M | Source, p. 141 → |
| Oct 2024 | Well 17 PFAS Removal., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $10.5M | Source, p. 141 → |
| Oct 2024 | Relocate existing GAC vessels to Well 29 and install new GAC Vessels at Wells 18 and 19 to address PFAS contamination, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $17.6M | Source, p. 141 → |
| Oct 2024 | Well 28 PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $6.68M | Source, p. 142 → |
| Undated | New Wellhead Treatment for PFAS Removal at Well 23, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Undated | Well 12 PFAS removal, Upgrade Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Oct 2025 | Installation of Ion Exchange to remove PFAS, Upgrade Water Treatment Plant On the FFY2026 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $1M | Source, p. 64 → |
| Oct 2025 | Installation of Ion Exchange to remove PFAS, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $1M | Source, p. 163 → |
| Nov 1, 2024 | Town of Kent Water District 1 and 2 PFAS Treatment 2024 WIIA grant awarded (Governor's announcement) | $703k | Source → |
| Oct 2024 | Installation of Ion Exchange to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $1M | Source, p. 108 → |
| Oct 2024 | Installation of Ion Exchange to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $1M | Source, p. 61 → |
| Oct 2024 | Installation of Ion Exchange to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $1M | Source, p. 155 → |
| Oct 2025 | Address PFAS, Develop Additional GW Source, Storage and Distribution Improvements., Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Storage, Upgrade Distribution System "Financed through SRF Market Rate Program" per FFY2026 Final IUP Annual List | $0 | Source, p. 65 → |
| Oct 2025 | Address PFAS, Develop Additional GW Source, Storage and Distribution Improvements., Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Storage, Upgrade Distribution System On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 164 → |
| Oct 2024 | Address PFAS, Develop Additional GW Source, Storage and Distribution Improvements., Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Storage, Upgrade Distribution System "Financed through SRF Market Rate Program" per FFY2025 Final IUP Annual List | $0 | Source, p. 62 → |
| Oct 2024 | Address PFAS, Develop Additional GW Source, Storage and Distribution Improvements., Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Storage, Upgrade Distribution System On the FFY2025 Multi-Year List (listing form submitted) | $0 | Source, p. 155 → |
| Oct 2025 | Creation of Poestenkill WD #2 to provide water to an area with PFAS contamination, New Water District Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $5.71M | Source, p. 59 → |
| Oct 2025 | Creation of Poestenkill WD #2 to provide water to an area with PFAS contamination, New Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $5.71M | Source, p. 163 → |
| Aug 14, 2025 | This project consists of the development of the Town of Poestenkill Water District No. 2. Work includes installation of approximately 36,000 linear feet new watermain and associated appurtenances along Route 66, Reichards Lake Road, and Vosburgh Road, and a new 200,000-gallon water storage tank to provide public water to 200 residential and commercial properties and a public school that are currently served by private wells contaminated with PFAS. The project scope is further defined by the engineering report titled ″Proposed Water District No. 2 Map, Plan and Report″, dated August 2022, by Laberge Group as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3087, 2025-08-14) | $670k | Source, p. 13 → |
| Aug 14, 2025 | This project consists of the development of the Town of Poestenkill Water District No. 2. Work includes installation of approximately 36,000 linear feet new watermain and associated appurtenances along Route 66, Reichards Lake Road, and Vosburgh Road, and a new 200,000-gallon water storage tank to provide public water to 200 residential and commercial properties and a public school that are currently served by private wells contaminated with PFAS. The project scope is further defined by the engineering report titled ″Proposed Water District No. 2 Map, Plan and Report″, dated August 2022, by Laberge Group as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3087, 2025-08-14) | $3.33M | Source, p. 17 → |
| Oct 2024 | Creation of Poestenkill WD #2 to provide water to an area with PFAS contamination, New Water District Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $5.71M | Source, p. 57 → |
| Oct 2024 | Creation of Poestenkill WD #2 to provide water to an area with PFAS contamination, New Water District On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $5.71M | Source, p. 155 → |
| Oct 2025 | Installation of GAC treatment to remove PFAS at Hewlett Well No. 4, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 48 → |
| Oct 2025 | New GAC to remove PFAS contamination at Ricks Well 7, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 55 → |
| Oct 2025 | New GAC to remove PFAS contamination at Well 6, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 77 → |
| Oct 2025 | Installation of GAC treatment to remove PFAS at Hewlett Well No. 4, Upgrade Water Treatment Plant Short-term loan closed (per FFY2026 Final IUP Multiyear List note) | $0 | Source, p. 147 → |
| Oct 2025 | New GAC to remove PFAS contamination at Ricks Well 7, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 148 → |
| Oct 2025 | New GAC to remove PFAS contamination at Well 6, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 149 → |
| Aug 14, 2025 | This project consists of the construction of a Granular Activated Carbon (GAC) treatment system for the removal of PFOA and PFOS from Sandy Hollow Wells 1 & 2. The existing pair of GAC treatment vessels will be upsized from 20,000-lb capacity to 40,000-lb capacity, providing greater treatment ability to remove PFOA and PFOS from the source water. The project is defined by the engineering report entitled ″PFAS Treatment at Sandy Hollow Road Well No. 1 and 2 Facility″ dated May 2024 by the engineering firm D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3087, 2025-08-14) | $5M | Source, p. 17 → |
| Jun 26, 2025 | This project consists of the construction of an upsized Granular Activated Carbon (GAC) treatment system for the removal of perfluorooctanoic acid (PFOA) and perfluorooctanesulfonic acid (PFOS) from existing Hewlett Well No. 4. The existing pair of GAC treatment vessels will be upsized from 20,000-lb capacity to 40,000-lb capacity, providing greater treatment ability to remove PFOA and PFOS from the source water. The project is defined by the engineering report entitled ″PFAS Treatment Enhancement at Hewlett Well 4″ dated June 2023 by the engineering firm D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3083, 2025-06-26) | $996k | Source, p. 97 → |
| Jun 26, 2025 | This project consists of the construction of an upsized Granular Activated Carbon (GAC) treatment system for the removal of perfluorooctanoic acid (PFOA) and perfluorooctanesulfonic acid (PFOS) from existing Hewlett Well No. 4. The existing pair of GAC treatment vessels will be upsized from 20,000-lb capacity to 40,000-lb capacity, providing greater treatment ability to remove PFOA and PFOS from the source water. The project is defined by the engineering report entitled ″PFAS Treatment Enhancement at Hewlett Well 4″ dated June 2023 by the engineering firm D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3083, 2025-06-26) | $4M | Source, p. 99 → |
| May 22, 2025 | This project consists of the construction of a Granular Activated Carbon (GAC) treatment system for the removal of PFOA and PFOS from the existing Well No. 6. The project is defined by the engineering report entitled “PFAS Treatment at Bar Beach Well 6” dated June 2023 by the engineering firm D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3075, 2025-05-22) | $5M | Source, p. 53 → |
| Jan 23, 2025 | This project consists of the construction of a Granular Activated Carbon treatment system for the removal of PFOA and PFOS from existing Well No. 7. The project is defined by the engineering report entitled "PFAS Treatment at Ricks Well 7" dated August 2022 by the engineering firm D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3064, 2025-01-23) | $5M | Source, p. 17 → |
| Oct 2024 | New GAC to remove PFAS contamination at Ricks Well 7, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $9.53M | Source, p. 54 → |
| Oct 2024 | New GAC to remove PFAS contamination at Well 6, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $8.19M | Source, p. 72 → |
| Oct 2024 | Installation of GAC treatment to remove PFAS at Hewlett Well No. 4, Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $7.72M | Source, p. 54 → |
| Oct 2024 | New GAC to remove PFAS contamination at Ricks Well 7, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $9.53M | Source, p. 108 → |
| Oct 2024 | Installation of GAC treatment to remove PFAS at Hewlett Well No. 4, Upgrade Water Treatment Plant On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $7.72M | Source, p. 108 → |
| Oct 2024 | Installation of GAC to treat PFAS, Improvements to site buildings and electric service., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $12.4M | Source, p. 139 → |
| Oct 2024 | New GAC to remove PFAS contamination at Ricks Well 7, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $9.53M | Source, p. 140 → |
| Oct 2024 | Installation of GAC treatment to remove PFAS at Hewlett Well No. 4, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $7.72M | Source, p. 140 → |
| Oct 2024 | New GAC to remove PFAS contamination at Well 6, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $8.19M | Source, p. 142 → |
| Undated | New GAC to remove PFAS contamination at Ricks Well 7, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $3.41M | Source, p. 2 → |
| Undated | Installation of GAC treatment to remove PFAS at Hewlett Well No. 4, Upgrade Water Treatment Plant IIJA-EC grant awarded (FFY2025 IUP awarded-projects list) (amount is the project cost) | $996k | Source, p. 2 → |
| Undated | New GAC to remove PFAS contamination at Well 6, Upgrade Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Oct 2025 | Enhance interconnection with Red Hook (T); eliminate Well #4 due to PFAS, Upgrade Storage, Upgrade Distribution System, Upgrade Inter-Connection "Financed through SRF Market Rate Program" per FFY2026 Final IUP Annual List | $0 | Source, p. 95 → |
| Oct 2025 | Enhance interconnection with Red Hook (T); eliminate Well #4 due to PFAS, Upgrade Storage, Upgrade Distribution System, Upgrade Inter-Connection On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 136 → |
| May 22, 2025 | This project consists of the decommissioning/abandonment of Well #4, replacement of approximately 2,400 linear feet of existing water main, hydrants, and lead service connections on Graves and Cherry Street, rehabilitation of the interior of the existing 225,000-gallon water tower located at the end of Tower Street, and replacement of the control system at the water treatment plant. The project is defined by the engineering report entitled ″PFOA/S Removal and Resilience Upgrades″ dated August 2022 by Delaware Engineering, D.P.C., as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3075, 2025-05-22) | $915k | Source, p. 52 → |
| May 22, 2025 | This project consists of the decommissioning/abandonment of Well #4, replacement of approximately 2,400 linear feet of existing water main, hydrants, and lead service connections on Graves and Cherry Street, rehabilitation of the interior of the existing 225,000-gallon water tower located at the end of Tower Street, and replacement of the control system at the water treatment plant. The project is defined by the engineering report entitled ″PFOA/S Removal and Resilience Upgrades″ dated August 2022 by Delaware Engineering, D.P.C., as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3075, 2025-05-22) | $1.08M | Source, p. 58 → |
| Oct 2024 | Enhance interconnection with Red Hook (T); eliminate Well #4 due to PFAS, Upgrade Storage, Upgrade Distribution System, Upgrade Inter-Connection "Financed through SRF Market Rate Program" per FFY2025 Final IUP Annual List | $0 | Source, p. 88 → |
| Oct 2024 | Enhance interconnection with Red Hook (T); eliminate Well #4 due to PFAS, Upgrade Storage, Upgrade Distribution System, Upgrade Inter-Connection On the FFY2025 Multi-Year List (listing form submitted) | $0 | Source, p. 128 → |
| Oct 2025 | New GAC Treatment to Address PFAS at Wells 3 & 4., New Water Treatment Plant, Upgrade Ground Water Source Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List | $0 | Source, p. 79 → |
| Oct 2025 | New GAC Treatment to Address PFAS at Wells 3 & 4., New Water Treatment Plant, Upgrade Ground Water Source On the FFY2026 Multi-Year List (listing form submitted) | $0 | Source, p. 149 → |
| Oct 2024 | New GAC Treatment to Address PFAS at Wells 3 & 4., New Water Treatment Plant, Upgrade Ground Water Source Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $10.6M | Source, p. 74 → |
| Oct 2024 | New GAC Treatment to Address PFAS at Wells 3 & 4., New Water Treatment Plant, Upgrade Ground Water Source On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $10.6M | Source, p. 140 → |
| Undated | New GAC Treatment to Address PFAS at Wells 3 & 4., New Water Treatment Plant, Upgrade Ground Water Source BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $5M | Source, p. 2 → |
| Oct 2025 | New Ground Water Source New South Water District to extend public water to consolidate PWSs with PFAS and 1,4-dioxane, New Water District Coded BGS ("Awarded IIJA-GS Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $27.6M | Source, p. 52 → |
| Oct 2025 | New South Water District to extend public water to consolidate PWSs with PFAS and 1,4-dioxane, New Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $27.6M | Source, p. 162 → |
| Undated | New South Water District to extend public water to consolidate PWSs with PFAS and 1,4-dioxane, New Water District IIJA-GS grant awarded (FFY2025 IUP awarded-projects list) | — | Source, p. 1 → |
| Oct 2025 | Morrisonville WD Sands Road Extension to serve PFOA contaminated private wells., New Distribution System, New System Consolidation Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $5.5M | Source, p. 51 → |
| Oct 2025 | Morrisonville WD Sands Road Extension to serve PFOA contaminated private wells., New Distribution System, New System Consolidation On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $5.5M | Source, p. 133 → |
| Oct 2024 | Morrisonville WD Sands Road Extension to serve PFOA contaminated private wells., New Distribution System, New System Consolidation Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $5.5M | Source, p. 50 → |
| Oct 2024 | Morrisonville WD Sands Road Extension to serve PFOA contaminated private wells., New Distribution System, New System Consolidation On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $5.5M | Source, p. 124 → |
| Oct 2025 | New drinking water distribution system to address PFAS contamination, New Distribution System, New Water District Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $2.91M | Source, p. 52 → |
| Oct 2025 | New drinking water distribution system to address PFAS contamination, New Distribution System, New Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $2.91M | Source, p. 178 → |
| Oct 2024 | New drinking water distribution system to address PFAS contamination, New Distribution System, New Water District Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $2.91M | Source, p. 51 → |
| Oct 2024 | New drinking water distribution system to address PFAS contamination, New Distribution System, New Water District On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $2.91M | Source, p. 170 → |
| Undated | New drinking water distribution system to address PFAS contamination, New Distribution System, New Water District BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $291k | Source, p. 2 → |
| Oct 2025 | Starr Ridge - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant Coded BEC ("Awarded IIJA-EC Funding") on the FFY2026 Final IUP Annual List (amount is the project cost) | $3M | Source, p. 64 → |
| Oct 2025 | Starr Ridge - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $3M | Source, p. 163 → |
| Oct 2024 | Starr Ridge - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $3M | Source, p. 61 → |
| Oct 2024 | Starr Ridge - Installation of GAC treatment to address PFAS contamination, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $3M | Source, p. 155 → |
| Oct 2025 | PFAS Removal, Upgrade Water Treatment Plant Short-term loan closed (per FFY2026 Final IUP Annual List note) | $0 | Source, p. 48 → |
| Oct 2025 | PFAS Removal, Upgrade Water Treatment Plant Short-term loan closed (per FFY2026 Final IUP Multiyear List note) | $0 | Source, p. 164 → |
| Jan 23, 2025 | ·This project includes the rehabilitation of three existing granular activated carbon (GAC) filter vessels that have been offline for 30 years. Work includes replacement of existing GAC media within the vessels, replacement of fiberglass pipe and fittings with ductile iron, and the installation of new chemical injection lines. The project scope is further defined by the engineering report entitled "Village of Suffern PFOS/PFOA Treatment System Engineer's Report", dated June 2022, by Pitingaro & Doetsch Consulting Engineers, P.C., as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3064, 2025-01-23) | $532k | Source, p. 17 → |
| Jan 23, 2025 | This project includes the rehabilitation of three existing granular activated carbon (GAC) filter vessels that have been offline for 30 years. Work includes replacement of existing GAC media within the vessels, replacement of fiberglass pipe and fittings with ductile iron, and the installation of new chemical injection . lines. The project scope is further defined by the engineering report entitled "Village of Suffern PFOS/PFOA Treatment System Engineer's Report", dated June 2022, by Pitingaro & Doetsch Consulting Engineers, P.C., as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3064, 2025-01-23) | $320k | Source, p. 20 → |
| Oct 2024 | PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $533k | Source, p. 54 → |
| Oct 2024 | PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $533k | Source, p. 156 → |
| Oct 2025 | State Street - GAC treatment for PFOA/PFOS removal and raising wellhead, Upgrade Water Treatment Plant, Upgrade Ground Water Source On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $14.4M | Source, p. 149 → |
| Jan 23, 2025 | This project consists of installation of two pairs of Granular Activated Carbon (GAC) adsorption vessels and all associated piping, valves, and appurtenances to treat perfluoroalkyl substances (PFAS) contamination, specifically perfluorooctanoic acid (PFOA) and perfluorooctanesulfonic acid (PFOS), at Well Nos. 15 and 18. Other work includes electrical service improvements and construction of a GAC room within the treatment facility. The project scope is further defined by the engineering report entitled, "PFAS Treatment at Wells 15 and 18" dated August 2022 (Revised December 2023), by D&B Engineers and Architects as may be updated, amended, supplemented, and approved by the New York State Department of Health. I.D. No. 3 01/23/2025 Approved by EFC Board of Directors (Resolution 3064, 2025-01-23) | $5M | Source, p. 20 → |
| Oct 2024 | Installation of new GAC system at the Wells 15 and 18 facility for PFAS removal, New Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $11.1M | Source, p. 141 → |
| Oct 2024 | State Street - GAC treatment for PFOA/PFOS removal and raising wellhead, Upgrade Water Treatment Plant, Upgrade Ground Water Source On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $14.4M | Source, p. 141 → |
| Aug 22, 2024 | 19099 Westbury Water Nassau $8,976,000 District Proiect Description This project is for the design and construction of a new treatment process at the existing water treatment facility to remove nitrate, volatile organic compounds (VOCs), 1 ,4- dioxane, and perfluorooctanoic acid (PFOA) from Well Nos. 10 and 14. The project includes the construction of a new ion exchange treatment system to remove nitrate, installation of a packed tower aeration system to remove voes after the anion exchange system, and an Advanced Oxidation Process (AOP) treatment system to remove 1,4-dioxane from the raw water. A proposed Granular Activated Carbon (GAC) treatment system will be used to quench residual hydrogen peroxide, and to remove potential AOP byproducts, additional voes, and PFOA. The facility will be designed to treat blended raw water from Well Nos. 10 and 14 at a combined rate of 2,750 gallons per minute (gpm). The project is defined by the engineering report entitled "1,4- Dioxane and PFOA Removal at Wells 10 and 14" dated November 2023 by D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health (NYSDOH). Approved by EFC Board of Directors (Resolution 3045, 2024-08-22) | $8.98M | Source, p. 36 → |
| Aug 14, 2025 | This project consists of the installation of two granular activated carbon (GAC) adsorption treatment systems and associated appurtenances at Well No. 6 to treat perfluorooctanoic acid (PFOA) and perfluorooctane sulfonic acid (PFOS) contamination. This project also includes the installation of a permanent treatment building to house the GAC vessels. Other work consists of replacement of the Well No. 6 pump and motor, raising the well to 18″ above grade, replacement of the blowoff/discharge piping and valves, replacement of the sodium hypochlorite feed system, as well as miscellaneous equipment upgrades and site improvements. The project scope is further defined by the engineering report dated December 2024, by D&B Engineers and Architects as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3087, 2025-08-14) | $5M | Source, p. 16 → |
| Oct 10, 2024 | The project includes installation of a new granular activated carbon (GAC) filtration system to remove perfluorooctanoic acid (PFOA) and perfluorooctanesulfonic acid (PFOS) at Well No. 1. Other improvements include site piping modifications, construction of a new treatment building, electrical upgrades, and a new well pump. The project scope is defined by the engineering report entitled "PFAS Removal at Well No. 1 ", dated October 2023 by the engineering firm D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3053, 2024-10-10) | $5M | Source, p. 102 → |
| Oct 2024 | Well 1 PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $9.71M | Source, p. 73 → |
| Oct 2024 | Well 1 PFAS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $9.71M | Source, p. 141 → |
| Oct 2024 | Installation of GAC treatment system to address PFAS contamination at Well No. 6, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $8.75M | Source, p. 141 → |
| Jun 26, 2025 | This project consists of installation of an advanced oxidation process (AOP) treatment system for the removal of 1,4-dioxane, and a granular activated carbon (GAC) treatment system for removal of PFOA and PFOS at the Ridge Road Well Site Plant No.2. The project scope is further defined by the engineering report entitled ″Wellhead Treatment for Emerging Contaminants at Ridge Road Well Site″, dated June 2023, revised September 2023, by H2M Architects + Engineers as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3083, 2025-06-26) | $4.62M | Source, p. 99 → |
| Oct 2024 | Plant No. 2 AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $13.3M | Source, p. 141 → |
| Apr 17, 2025 | The project includes installation of a new groundwater well and/or installation of treatment for the existing well that is currently contaminated with perfluorononanoic acid (PFNA). The village will prioritize development of a new well source to replace the PFNA contaminated well. If unsuccessful, new treatment will be added to the existing source to remove PFNA. In addition, the project includes replacement of approximately 26,000 linear feet of aged and deteriorated watermains in various areas within the water system. The project is defined by the preliminary engineering report entitled ″Water System Improvements Project″ dated June 2023 by the engineering firm Barton & Loguidice, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3071, 2025-04-17) | — | Source, p. 6 → |
| Nov 1, 2024 | Pabst Water System PFOS Mitigation Project 2024 WIIA grant awarded (Governor's announcement) | $592k | Source → |
| Nov 1, 2024 | PFAS Treatment at Plant No. 6 2024 WIIA grant awarded (Governor's announcement) | $3.48M | Source → |
| Oct 10, 2024 | This project consists of the installation of two granular activated carbon (GAC) adsorption treatment systems and associated appurtenances at wells 3 and 4 to treat perfluorooctanoic acid (PFOA) and perfluorooctane sulfonic acid (PFOS) contamination. This project also includes the installation of a permanent treatment building and associated electric work to house the GAC vessels. Other work included consists of new centralized chemical storage, feed, and safety systems within the proposed treatment building, site blow-off improvements, as well as miscellaneous equipment upgrades/improvements to existing piping, valves, and appurtenances. The project scope is further defined by the engineering report dated August 2022 (revised April 2023), by D&B Engineers and Architects, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3053, 2024-10-10) | $4.59M | Source, p. 100 → |
| Oct 2024 | Installation of GAC system for treatment of PFAS at Wells 3 & 4, Upgrade Water Treatment Plant Coded BEC ("Awarded BIL-EC Funding") on the FFY2025 Final IUP Annual List (amount is the project cost) | $7.65M | Source, p. 73 → |
| Oct 2024 | Installation of GAC system for treatment of PFAS at Wells 3 & 4, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $7.65M | Source, p. 141 → |
| Undated | Installation of GAC system for treatment of PFAS at Wells 3 & 4, Upgrade Water Treatment Plant BIL-EC grant awarded (FFY2024 IUP awarded-projects list) (amount is the project cost) | $411k | Source, p. 2 → |
| Oct 10, 2024 | This project consists of the installation of a Granular Activated Carbon (GAC) treatment system at the Roslyn Water District (WO) Plant No. 5 to remove PFAS. The project is defined by the engineering report entitled "Engineering Contaminant Removal at Plant No. 5" dated March 2023 by the engineering firm H2M architects+ engineers, as may be updated, amended, supplemented, and approved by the New York State Department of Health. Approved by EFC Board of Directors (Resolution 3053, 2024-10-10) | $2.98M | Source, p. 102 → |
| Oct 2025 | Installation of GAC for PFAS, new well, new disinfection, Upgrade Water Treatment Plant, New Ground Water Source On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $669k | Source, p. 55 → |
| Oct 2025 | Installation of GAC for PFAS, new well, new disinfection, Upgrade Water Treatment Plant, New Ground Water Source On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $669k | Source, p. 140 → |
| Oct 2024 | Installation of GAC for PFAS, new well, new disinfection, Upgrade Water Treatment Plant, New Ground Water Source On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $669k | Source, p. 54 → |
| Oct 2024 | Installation of GAC for PFAS, new well, new disinfection, Upgrade Water Treatment Plant, New Ground Water Source On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $669k | Source, p. 131 → |
| Oct 2025 | New Groundwater Well Installation & Source Capacity Expansion to address existing sources with 1,4-dioxane and PFAS, Aged Main Replacement & Extension, Storage Tank Replacements, Wellhouse Improvements, New Ground Water Source On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $40.5M | Source, p. 52 → |
| Oct 2025 | New Groundwater Well Installation & Source Capacity Expansion to address existing sources with 1,4-dioxane and PFAS, Aged Main Replacement & Extension, Storage Tank Replacements, Wellhouse Improvements, New Ground Water Source On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $40.5M | Source, p. 129 → |
| Oct 2025 | New treatment for PFOA/PFOS removal, new well, water main replacement., New Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $4.15M | Source, p. 59 → |
| Oct 2025 | New treatment for PFOA/PFOS removal, new well, water main replacement., New Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $4.15M | Source, p. 163 → |
| Oct 2025 | PFOS removal at Lincoln Street Wells, Upgrade Water Treatment Plant On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $4.61M | Source, p. 55 → |
| Oct 2025 | PFOS removal at Lincoln Street Wells, Upgrade Water Treatment Plant On the FFY2026 IIJA-GS Eligible Project List (amount is the project cost) | $4.61M | Source, p. 109 → |
| Oct 2025 | PFOS removal at Lincoln Street Wells, Upgrade Water Treatment Plant On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $4.61M | Source, p. 118 → |
| Oct 2025 | PFOS removal at Lincoln Street Wells, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $4.61M | Source, p. 147 → |
| Oct 2024 | PFOS removal at Lincoln Street Wells, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $1.01M | Source, p. 139 → |
| Oct 2025 | Expand GW Source Capacity to address source capacity and replace well with PFAS, Replace Aging & Asbestos Main & Looping, Replace Storage Tank, Upgrade Ground Water Source, New Storage, Upgrade Distribution System On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $14.4M | Source, p. 51 → |
| Oct 2025 | Expand GW Source Capacity to address source capacity and replace well with PFAS, Replace Aging & Asbestos Main & Looping, Replace Storage Tank, Upgrade Ground Water Source, New Storage, Upgrade Distribution System On the FFY2026 IIJA-GS Eligible Project List (amount is the project cost) | $14.4M | Source, p. 109 → |
| Oct 2025 | Expand GW Source Capacity to address source capacity and replace well with PFAS, Replace Aging & Asbestos Main & Looping, Replace Storage Tank, Upgrade Ground Water Source, New Storage, Upgrade Distribution System On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $14.4M | Source, p. 131 → |
| Oct 2025 | PFAS Treatment, Upgrade Water Treatment Plant On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $3.42M | Source, p. 61 → |
| Oct 2025 | PFAS Treatment, Upgrade Water Treatment Plant On the FFY2026 IIJA-GS Eligible Project List (amount is the project cost) | $3.42M | Source, p. 111 → |
| Oct 2025 | PFAS Treatment, Upgrade Water Treatment Plant On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $3.42M | Source, p. 118 → |
| Oct 2025 | PFAS Treatment, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $3.42M | Source, p. 158 → |
| Oct 2025 | Treatment of PFAS, iron and manganese, Upgrade Water Treatment Plant On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $5.06M | Source, p. 59 → |
| Oct 2025 | Treatment of PFAS, iron and manganese, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $5.06M | Source, p. 163 → |
| Oct 2025 | Water District Extension to consolidate mulitple PWSs with PFAS, Storage Tank Installation, Pumpstation Upgrades, Extend Distribution System On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $26.3M | Source, p. 51 → |
| Oct 2025 | Water District Extension to consolidate mulitple PWSs with PFAS, Storage Tank Installation, Pumpstation Upgrades, Extend Distribution System On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $26.3M | Source, p. 118 → |
| Oct 2025 | Water District Extension to consolidate mulitple PWSs with PFAS, Storage Tank Installation, Pumpstation Upgrades, Extend Distribution System On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $26.3M | Source, p. 154 → |
| Oct 2025 | Removal of sodium chloride and PFAS from water system, Upgrade Water Treatment Plant On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $953k | Source, p. 57 → |
| Oct 2025 | Removal of sodium chloride and PFAS from water system, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $953k | Source, p. 178 → |
| Oct 2024 | Removal of sodium chloride and PFAS from water system, Upgrade Water Treatment Plant On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $953k | Source, p. 56 → |
| Oct 2024 | Removal of sodium chloride and PFAS from water system, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $953k | Source, p. 170 → |
| Oct 2025 | Quaker Hill WS Interconnection with Hyde Park Regional WS to resolve PFAS contamination at Quaker Hill., New Pump Station, New Inter-Connection On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $21.9M | Source, p. 56 → |
| Oct 2025 | Quaker Hill WS Interconnection with Hyde Park Regional WS to resolve PFAS contamination at Quaker Hill., New Pump Station, New Inter-Connection On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $21.9M | Source, p. 135 → |
| Oct 2024 | Quaker Hill WS Interconnection with Hyde Park Regional WS to resolve PFAS contamination at Quaker Hill., New Pump Station, New Inter-Connection On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $21.9M | Source, p. 54 → |
| Oct 2024 | Quaker Hill WS Interconnection with Hyde Park Regional WS to resolve PFAS contamination at Quaker Hill., New Pump Station, New Inter-Connection On the FFY2025 BIL-GS Eligible Project List (amount is the project cost) | $21.9M | Source, p. 100 → |
| Oct 2024 | Quaker Hill WS Interconnection with Hyde Park Regional WS to resolve PFAS contamination at Quaker Hill., New Pump Station, New Inter-Connection On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $21.9M | Source, p. 108 → |
| Oct 2024 | Quaker Hill WS Interconnection with Hyde Park Regional WS to resolve PFAS contamination at Quaker Hill., New Pump Station, New Inter-Connection On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $21.9M | Source, p. 127 → |
| Oct 2025 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $10.9M | Source, p. 59 → |
| Oct 2025 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2026 IIJA-GS Eligible Project List (amount is the project cost) | $10.9M | Source, p. 110 → |
| Oct 2025 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $10.9M | Source, p. 178 → |
| Oct 2024 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2025 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $10.9M | Source, p. 57 → |
| Oct 2024 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2025 BIL-GS Eligible Project List (amount is the project cost) | $10.9M | Source, p. 100 → |
| Oct 2024 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2025 BIL-EC Eligible Project List (amount is the project cost) | $10.9M | Source, p. 108 → |
| Oct 2024 | Creation of the Scotts Corners WD to Serve Contaminated Private Wells, Consolidate Several Public Water Systems, and Address PFAS, New Water District On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $10.9M | Source, p. 170 → |
| Oct 2025 | New WTP to treat PFAS, new wells, watermain replacement, SCADA upgrade, New Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 Annual List above the Expanded Subsidized Interest Rate Funding Line (amount is the project cost) | $10.3M | Source, p. 54 → |
| Oct 2025 | New WTP to treat PFAS, new wells, watermain replacement, SCADA upgrade, New Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 IIJA-GS Eligible Project List (amount is the project cost) | $10.3M | Source, p. 109 → |
| Oct 2025 | New WTP to treat PFAS, new wells, watermain replacement, SCADA upgrade, New Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 IIJA-EC Eligible Project List (amount is the project cost) | $10.3M | Source, p. 118 → |
| Oct 2025 | New WTP to treat PFAS, new wells, watermain replacement, SCADA upgrade, New Water Treatment Plant, New Ground Water Source, Upgrade Distribution System On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $10.3M | Source, p. 139 → |
| Oct 2025 | Installation of single-use ion exchange media to remove high levels of PFAS and perchlorate, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $14.1M | Source, p. 148 → |
| Oct 2024 | Installation of single-use ion exchange media to remove high levels of PFAS and perchlorate, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $14.1M | Source, p. 139 → |
| Oct 2025 | Jackson Ave GAC filtration for PFAS Removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $2.47M | Source, p. 160 → |
| Oct 2024 | Jackson Ave GAC filtration for PFAS Removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $2.47M | Source, p. 153 → |
| Oct 2025 | Wells No. 7 and 10 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $6.5M | Source, p. 148 → |
| Oct 2024 | Wells No. 7 and 10 - GAC treatment for PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $6.5M | Source, p. 140 → |
| Oct 2025 | Construction of GAC filters to remove PFAS, Upgrade Water Treatment Plant On the FFY2026 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $14.7M | Source, p. 78 → |
| Oct 2025 | Construction of GAC filters to remove PFAS, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $14.7M | Source, p. 158 → |
| Oct 2024 | Construction of GAC filters to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $14.7M | Source, p. 73 → |
| Oct 2024 | Construction of GAC filters to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $14.7M | Source, p. 150 → |
| Oct 2025 | PFAS Treatment and Water System Improvements, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $834k | Source, p. 163 → |
| Oct 2025 | Install treatment to remove PFAS, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $1.01M | Source, p. 128 → |
| Oct 2024 | Install treatment to remove PFAS, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $1.01M | Source, p. 120 → |
| Oct 2025 | Shoremont WTP - Replacement of GAC media to remove PFOA/PFOS, Upgrade Water Treatment Plant On the FFY2026 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $3.05M | Source, p. 96 → |
| Oct 2025 | Shoremont WTP - Replacement of GAC media to remove PFOA/PFOS, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $3.05M | Source, p. 147 → |
| Oct 2024 | Shoremont WTP - Replacement of GAC media to remove PFOA/PFOS, Upgrade Water Treatment Plant On the FFY2025 Annual List below the Expanded Subsidized Interest Rate Funding Line (market-rate only) (amount is the project cost) | $3.05M | Source, p. 88 → |
| Oct 2024 | Shoremont WTP - Replacement of GAC media to remove PFOA/PFOS, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $3.05M | Source, p. 139 → |
| Oct 2025 | Installation of PFAS removal system., Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $846k | Source, p. 178 → |
| Oct 2024 | Installation of PFAS removal system., Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $846k | Source, p. 170 → |
| Oct 2025 | Plant No. 4 - AOP/GAC treatment for 1,4-Dioxane and PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $7.24M | Source, p. 172 → |
| Oct 2024 | Plant No. 4 - AOP/GAC treatment for 1,4-Dioxane and PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $7.24M | Source, p. 164 → |
| Oct 2025 | New ion exchange treatment system for PFOS/PFOA removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $92k | Source, p. 178 → |
| Oct 2024 | New ion exchange treatment system for PFOS/PFOA removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $92k | Source, p. 170 → |
| Oct 2025 | 1,4-dioxane, PFOA/PFOS, and nitrate treatment for Well Nos. 1A & 2A at Levittown WD, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $6M | Source, p. 147 → |
| Oct 2025 | 1,4-dioxane, PFOA/PFOS, and nitrate treatment for Well Nos. 7, 11 & 12 at Roosevelt WD, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $22M | Source, p. 148 → |
| Oct 2025 | Market Lane Plant Well Nos. 5A & 6B - AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $11.9M | Source, p. 148 → |
| Oct 2025 | 1,4-dioxane, PFOA/PFOS, and nitrate treatment for Wells No. 1 and 2 at Bowling Green Estates WD, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $9.5M | Source, p. 148 → |
| Oct 2024 | 1,4-dioxane, PFOA/PFOS, and nitrate treatment for Well Nos. 1A & 2A at Levittown WD, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $6M | Source, p. 139 → |
| Oct 2024 | Market Lane Plant Well Nos. 5A & 6B - AOP/GAC treatment for 1,4-dioxane and PFOA/PFOS removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $11.9M | Source, p. 140 → |
| Oct 2024 | 1,4-dioxane, PFOA/PFOS, and nitrate treatment for Well Nos. 7, 11 & 12 at Roosevelt WD, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $22M | Source, p. 140 → |
| Oct 2024 | East Meadow WD Wells No. 5 and 11 - AOP/GAC treatment for 1,4-dioxane, PFOA/PFOS, 1,1-DCA, and other VOCs removal, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $6.1M | Source, p. 140 → |
| Oct 2024 | 1,4-dioxane, PFOA/PFOS, and nitrate treatment for Wells No. 1 and 2 at Bowling Green Estates WD, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $9.5M | Source, p. 140 → |
| Oct 2025 | Well 6-2 PFAS Treatment, Upgrade Water Treatment Plant On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $5.79M | Source, p. 148 → |
| Oct 2024 | Well 6-2 PFAS Treatment, Upgrade Water Treatment Plant On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $5.79M | Source, p. 140 → |
| Oct 2025 | Upgrade storage tank, rehab well, new well, disinfection, and treatment of PFAS and iron, Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Storage, Upgrade Pump Station On the FFY2026 Multi-Year List (listing form submitted) (amount is the project cost) | $9.59M | Source, p. 158 → |
| Oct 2024 | Installation of GAC for PFOA/PFOS removal., Upgrade Water Treatment Plant, Upgrade Distribution System On the FFY2025 Multi-Year List (listing form submitted) (amount is the project cost) | $5.17M | Source, p. 128 → |